PMI Project-Management-Professional PMP Question # 273 Topic 30 Discussion

PMP Exam Topic 30 Question 273 Discussion:
Question #: 273
Topic #: 30

In a weak matrix environment, two key team members are falling behind with their tasks, which will affect the success of the project.

Further investigation by the project manager reveals that they have unresolved issues with each other. The project manager asks them to find a way to resolve the issues, but this is unsuccessful. The project manager then holds a meeting with them to work outa permanent solution to the issues, but this is also unsuccessful.

What should the project manager do next?


A.

Escalate the issue to a higher authority.


B.

Suspend the two key team members immediately.


C.

Put the issue on the agenda for the next team meeting.


D.

Reassign one of the key team members to a different task.