A product owner has provided the team with a prioritized backlog for the initial

launch of a new product. After analysis, the team concludes that some work is missing to

support the initial launch and provides this information to the product owner. The product

owner acknowledges the missing work and adds it to the bottom of the backlog. The team is

not happy with the prioritization that the missing work received.

What should the project manager do in this situation?


A.

Let the project team pull the recommended work from the bottom of the backlog to

maximize value creation.


B.

Analyze and reprioritize the backlog and provide the decision to the product owner

and team.


C.

Recommend the product owner prioritize the missing work higher because it is

needed for the minimum viable product (MVP).


D.

Empower the product owner by supporting the decision and instructing the team to follow the prioritization as provided.