PMI Project-Management-Professional PMP Question # 275 Topic 31 Discussion

PMP Exam Topic 31 Question 275 Discussion:
Question #: 275
Topic #: 31

A project manager is responsible for providing a budget estimate for a long-term project that will be executed over several years. Which essential task should the project manager implement at this phase?


A.

Include key risks in the cost baseline.


B.

Perform an analogous estimate.


C.

Perform a bottom-up estimate.


D.

Include projected inflation rates.