Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 285 Topic 32 Discussion

PMP Exam Topic 32 Question 285 Discussion:
Question #: 285
Topic #: 32

A project manager receives a call from the customer's account manager requesting support for a critical operational issue. Although the issue is unrelated to the project, the customer believes that one of the project team members has the technical expertise to recommend a solution.

What should the project manager do first?


A.

Organize a conference call with the internal expert and the client to estimate the amount of effort required to fix it.


B.

Decline the request politely since the issue, although critical, is not the responsibility of the project team.


C.

Allocate a task to the team member as a high priority and inform the customer that the issue will be resolved the next day.


D.

Inform the customer that they should contact the sales manager and submit a formal request for a quote.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.