A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?


A.

Escalate the issue to the team's manager.


B.

Remove some of the team members.


C.

Review the roles and responsibilities document.


D.

Develop working agreements with the team.