Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 300 Topic 33 Discussion

PMP Exam Topic 33 Question 300 Discussion:
Question #: 300
Topic #: 33

A new relevant project stakeholder suggested a change to some of the project parameters midway through execution What should the project manager do next?


A.

Accept the change and use contingency funds to implement this change with minimal schedule impacts


B.

Reject the change because it is contrary to what was agreed to during earlier phases of the project


C.

Transfer the change to the steering committee for them to evaluate and decide the appropriate next steps


D.

Evaluate the proposed change with integrated change controls and discuss the change with the project sponsor


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.