PMI Project-Management-Professional PMP Question # 301 Topic 33 Discussion

PMP Exam Topic 33 Question 301 Discussion:
Question #: 301
Topic #: 33

The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.

What should the project manager have done?


A.

Conveyed task completion information to accounting


B.

Closed the procurement process properly


C.

Completed the transition process


D.

Performed administrative closure of the project