A new agile project manager is trying to determine how the team is performing against the schedule for a release. Which tool will provide a deeper look into the team's progress?
A burndown chart is a graphical tool that shows the amount of work remaining versus the time available for a release or iteration. It helps the agile project manager and the team to monitor the progress and velocity of the work, identify any deviations or impediments, and adjust the plan accordingly. A burndown chart can provide a deeper look into the team’s progress than a release plan, a product roadmap, or a Kanban board, which are more high-level and strategic tools that show the scope, vision, and priorities of the project. 123 References: