Question #: 307
Topic #: 33

The operations director complains to the CEO about the outcome of a project's first sprint The operations department will not be able to support a new product due to poor performance indicators The project team facilitator asks for feedback from the project team and is informed that performance information is available in the application server log

How should this complaint be addressed?


A.

Request that the issue be included in the next board of directors meeting to explain all of the needs


B.

Add the complaint to the product backlog to be addressed in the next sprint


C.

Ask the operations director to define the acceptance criteria to make clear the delivery is correct


D.

Invite a member of the operations team to be part of the validation and sprint meetings