A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule.

What should the project manager do?


A.

Ensure that relevant stakeholders and expectations are identified and assess the component delay.


B.

Perform a detailed analysis of the release content for each component of the solution.


C.

Propose a new design of the solution to replace the external component with an internal one.


D.

Ask for expedited delivery of the component to mitigate the risk of schedule delays.