Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 314 Topic 34 Discussion

PMP Exam Topic 34 Question 314 Discussion:
Question #: 314
Topic #: 34

The portfolio management office wants to cut costs by suspending some ongoing

projects that do not directly support the organizational strategy. The project manager has invested too many resources into one of the projects to be suspended, but the portfolio

management office has not backed down on their plan.

What should the project manager do to continue the project?


A.

Meet with the project team and revise the project goals.


B.

Update the project charter to make it align with organizational strategy.


C.

Demonstrate the project alignment to the organizational strategy.


D.

Escalate the issue with the project sponsor to request support.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.