Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 316 Topic 34 Discussion

PMP Exam Topic 34 Question 316 Discussion:
Question #: 316
Topic #: 34

A company is transitioning from a predictive to agile delivery of projects. Based on

the requirements, the project team estimates the budget and decides to use a fixed-price

contract with its vendor. However, during the execution of the project, the requirements

evolve and priorities start to change constantly, which puts the project and the estimate at completion (EAC) off by 40%.

What should the project manager do next?


A.

Send a detailed status report highlighting the issue with funding to all of the stakeholders.


B.

Submit a change request to the financial manager to increase the funding and continue as is.


C.

Meet with the stakeholders to recommend the use of a time and materials (T&M) contract to address the problem.


D.

Wait until the next gate review meeting to highlight the risk of low funds to the stakeholders.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.