PMI Project-Management-Professional PMP Question # 321 Topic 35 Discussion

PMP Exam Topic 35 Question 321 Discussion:
Question #: 321
Topic #: 35

A project manager brings in a new team member from an agile environment to work in a predictive environment The project manager expects to leverage the new team member's agile experience with the existing team members.

What should the project manager do to integrate the new team member effectively?


A.

Train the new team member in the predictive project management approach.


B.

Acknowledge that hiring this new employee is a risk to the existing team


C.

Set expectations with the new team member and explain what is needed


D.

Meet with all team members and explain the new employee's position.