A project manager is assigned to a technical research project. The project team has

already been assigned, and the main subject matter expert (SME) sends the project

manager a list of the technical skills required for the execution of this project.

What should the project manager do next?


A.

Send the list to the project team and ask them to get training on the required skills.


B.

Ask the functional manager to review the resource pool and recommend the right individuals to join the team.


C.

Discuss the list with the project sponsor to confirm that the resources have the required skills.


D.

Meet with the project team to understand their skills and identify potential gaps and training requirements.