PMI Project-Management-Professional PMP Question # 332 Topic 36 Discussion

PMP Exam Topic 36 Question 332 Discussion:
Question #: 332
Topic #: 36

Team morale is at an all-time low after an incident involving one of the team members. Which two actions should the project manager take to resolve the situation? (Choose two)


A.

Host a special meeting to talk about what happened.


B.

Escalate the issue to human resources (HR).


C.

Review the lessons learned document with the team.


D.

Conduct a team-building workshop.


E.

Discuss this incident in the project review meeting.