On a transformational project, the project manager is confronted with resistance

from the stakeholders. To overcome this and gain acceptance of the change, what should

the project manager do first?


A.

Escalate the issue to the project sponsor.


B.

Review the stakeholder engagement plan.


C.

Update the issue log.


D.

Neutralize the negative stakeholders.