An organization in a regulated industry has decided to switch from a predictive to

an agile delivery approach. It has been decided that the ongoing projects will adopt Scrum,

and the project manager is still accountable for the project outcomes. During the fourth sprint

demo, the customer notices that a feature is not compliant with the regulations.

What should the project manager do?


A.

Have the team consult with the compliance officer to update the definition of done

(DoD) for the user stories in the past sprint.


B.

Have the product owner consult with the change control board (CCB) to have the

necessary compliance requirements implemented.


C.

Have the scrum master organize a weekly meeting with the compliance officer, the

product owner, and the project team.


D.

Have the product owner review the user stories in the product backlog with the

compliance officer on a regular basis to identify any gaps.