An agile project has just started, and the backlog is being prioritized. The

customer wants to prioritize business value over identified risks.

How should the customer’s request be managed?


A.

Accept risks as they decrease over a period of time.


B.

Create a risk value profile to track the relative importance of risks.


C.

Log and track risks separately as only business value is important.


D.

Assess risks together with business value during prioritization.