PMI Project-Management-Professional PMP Question # 341 Topic 37 Discussion

PMP Exam Topic 37 Question 341 Discussion:
Question #: 341
Topic #: 37

The business manager and the product owner are requesting a more flexible way to incorporate changes into the product baseline They are concerned about losing time to market with respect to other vendors

What should the project manager do?


A.

Review the assumption log and project management plan for changes.


B.

Identify adequate change management tools to conduct the project


C.

Establish a change control board (CCB) with key stakeholders.


D.

Allow key stakeholders to make some changes to deliver the product faster