Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 349 Topic 37 Discussion

PMP Exam Topic 37 Question 349 Discussion:
Question #: 349
Topic #: 37

A company has hired a vendor to deliver a scope of work and assigned a project

manager to oversee the project. The vendor advised that they completed the scope

successfully and is asking for approval.

What should the project manager do in response to this request?


A.

Obtain approval from the project sponsor.


B.

Update the project management plan and mark the milestone as completed.


C.

Ask the vendor to validate the agreement for any deviations.


D.

Set up a meeting with stakeholders to validate and confirm acceptance of the deliverables.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.