Question #: 352
Topic #: 38

Due to a recent budget reduction, two team members were released from an agile

team. The customer is still expecting early results for the project.

Which two actions should the project manager take to align customer expectations? (Choose

two)


A.

Ask the agile team to review the updated sprint velocity with the customer.


B.

Ask the product owner to review the prioritized backlog with the customer.


C.

Ask the agile team to review and update the quality management plan with the

customer.


D.

Review the impediments log with the customer.


E.

Send a detailed project management plan to the customer.