Question #: 354
Topic #: 38

A project manager is managing a megaproject. The project stakeholders are from different geographical areas and have diverse cultural and social backgrounds. The project manager wants to improve team productivity to realize more effective and efficient results.

Which action should the project manager take?


A.

Empower team members to participate in decision-making and take ownership of actions.


B.

Implement a flexible work schedule policy to eliminate the time zone problems among stakeholders.


C.

Encourage team members to network so that they know each other's cultural backgrounds.


D.

Provide a relaxed work schedule policy and encourage team members to work from home.