PMI Project-Management-Professional PMP Question # 375 Topic 38 Discussion

PMP Exam Topic 38 Question 375 Discussion:
Question #: 375
Topic #: 38

In an agile project that is about 45% complete, most team members are siloed and lack an understanding of each other's work. What would have

most likely caused this communication breakdown?


A.

The sprint review meetings were not held regularly.


B.

The daily standup meetings were not consistently attended.


C.

The project manager failed to develop a communications management plan.


D.

The weekly project status reports were not published regularly.