PMI Project-Management-Professional PMP Question # 360 Topic 39 Discussion

PMP Exam Topic 39 Question 360 Discussion:
Question #: 360
Topic #: 39

The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to ‘move its go-live date. What should the project manager do next?


A.

Ensure that the project meets the committed time lines as this is the core objective and purpose of the project.


B.

Raise a change request to the change control board (CCB) to ask for funds to onboard new resources to expedite the project.


C.

Capture the risk in the risk register and monitor it to prevent it from becoming an issue by taking the proper response action.


D.

Ask the sponsor to start a new project to support the existing project and help it meet the original time line.