PMI Project-Management-Professional PMP Question # 388 Topic 39 Discussion

PMP Exam Topic 39 Question 388 Discussion:
Question #: 388
Topic #: 39

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

PMP Question 388


A.

Ask the product owner if some low-priority stories could be cut from the sprint.


B.

Continue with the sprint as the progress shows buffers for potential interruptions.


C.

Ask the project team to select any additional stories as they have additional capacity than planned.


D.

Continue with the sprint work as planned and keep monitoring.