PMI Project-Management-Professional PMP Question # 389 Topic 39 Discussion

PMP Exam Topic 39 Question 389 Discussion:
Question #: 389
Topic #: 39

A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change

requests issued due to the nature of the project.

What should the project manager do?


A.

Add a fixed number of change requests allowed by the client on the project baseline.


B.

Request sponsor approval for all change requests to reduce the number of changes.


C.

Initiate the number of iterations to reduce the number of change requests.


D.

Reduce the number of approvers required to implement a change request.