Question #: 34
Topic #: 4

A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.

How should the project manager ensure the product increments deliver the anticipated requirements?


A.

Appoint a dedicated product manager for the duration of the release


B.

Have the customer approve the product increment features.


C.

Ensure every user story has acceptance criteria.


D.

Track business outcomes for planned user stories.