PMI Project-Management-Professional PMP Question # 37 Topic 4 Discussion

PMP Exam Topic 4 Question 37 Discussion:
Question #: 37
Topic #: 4

A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?


A.

Request action from the functional manager regarding the team members poor performance


B.

Avoid selecting the team member to the next project that has an iterative design stage


C.

Provide feedback and coach the team member during the iterative design stage


D.

Escalate the issue to the human resources manager and request that the team member be replaced