One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests thai this might just be a small task.

What should the project manager do?


A.

Coordinate design document preparation


B.

Perform a qualitative risk analysis


C.

Request further clarification of the requirement


D.

Manage the engagement of this stakeholder.