A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.

What should the senior project manager do now?


A.

Use interpersonal skills to expedite the issue.


B.

Send a gentle reminder to the technical service team.


C.

Update the issue log with the status and priority.


D.

Issue a formal warning to the technical service team.