PMI Project-Management-Professional PMP Question # 410 Topic 43 Discussion

PMP Exam Topic 43 Question 410 Discussion:
Question #: 410
Topic #: 43

A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. Ina project review meeting, a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.

What should the project manager do?


A.

Ask the project management office (PMO) to support and review all deliverables.


B.

Log the issue in the risk register and the issue log.


C.

Assign a technical writer to the project.


D.

Develop a standard for document quality control.