PMI Project-Management-Professional PMP Question # 411 Topic 43 Discussion

PMP Exam Topic 43 Question 411 Discussion:
Question #: 411
Topic #: 43

A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.

Which risk management process should be performed?


A.

Plan Risk Responses, to outline the possible options to bypass the system performance issue


B.

Perform Qualitative Risk Analysis, to assess the extent of the system performance impact


C.

Monitor Risks, to install system performance monitoring tools and update the risk register


D.

Perform Quantitative Risk Analysis, to outline the details of the system performance issues