Question #: 420
Topic #: 44

In an agile project, some stakeholders are asking to have a meeting with the team every 2 weeks in order to understand project progress. What

should the project lead do next?


A.

Invite the stakeholders to the retrospective meetings.


B.

Invite the stakeholders to the sprint review meetings.


C.

Hold a meeting every 2 weeks with the stakeholders.


D.

Negotiate by sending an informative email to stakeholders.