A project manager has been assigned to manage multiple agile project teams. The project manager wants to empower the teams and make them self-organizing.
What should the project manager do to create a positive environment?
A.
Establish the team ground rules and share them with the team for strict adherence.
B.
Copy the ground rules established by another project and provide them to the teams.
C.
Extract the organization's policies and processes, customize them, and give them to the teams to adhere to.
D.
Help the teams in establishing and adhering to their ground rules and revisit after regular intervals.
In an Agile environment, the project manager’s role is to empower the teams and make them self-organizing12. This involves helping the teams establish their own ground rules and ensuring adherence to these rules3. It’s important to revisit these rules at regular intervals for continuous improvement2. This approach promotes collaboration, understanding, and strong leadership within the team1. It’s also crucial for the project manager to have excellent communication skills, the ability to identify and analyze potential risks, and the ability to motivate and mentor individuals and teams3. References:
Chosen Answer: