PMI Project-Management-Professional PMP Question # 427 Topic 44 Discussion

PMP Exam Topic 44 Question 427 Discussion:
Question #: 427
Topic #: 44

A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee,

* Actual progress = 2 units

* Planned progress = 3 units

* Actual cost (AC) = 2 units

* Budgeted cost = 3 units

What statement should the project manager make to the project steering committee?


A.

The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities.


B.

The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken.


C.

The project is currently behind schedule but at a lower cost, and an application for a time and budget extension will be submitted.


D.

The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings,