A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria.
How should the project manager ensure the acceptance criteria are ret?
A.
Perform tests and routinely track results as per the quality management plan.
B.
Make sure the stakeholders are aware of the acceptance criteria.
C.
Negotiate to obtain approval if most of the tests have passed.
D.
Modify the acceptance criteria before the official delivery.
According to the Project Management Body of Knowledge (PMBOK) guide, the project manager should ensure that the project meets the agreed acceptance criteria by performing tests and routinely tracking results as per the quality management plan. This approach allows the project manager to monitor the project’s progress and make necessary adjustments to ensure that the project meets the acceptance criteria. References: PMBOK Guide, 6th Edition, Section 8: Quality Management
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit