Weekend Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 428 Topic 44 Discussion

PMP Exam Topic 44 Question 428 Discussion:
Question #: 428
Topic #: 44

A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria.

How should the project manager ensure the acceptance criteria are ret?


A.

Perform tests and routinely track results as per the quality management plan.


B.

Make sure the stakeholders are aware of the acceptance criteria.


C.

Negotiate to obtain approval if most of the tests have passed.


D.

Modify the acceptance criteria before the official delivery.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.