PMI Project-Management-Professional PMP Question # 430 Topic 45 Discussion

PMP Exam Topic 45 Question 430 Discussion:
Question #: 430
Topic #: 45

One of the team members is always late to the daily standup meeting. What should the project manager do?


A.

Schedule the meeting at the end of the day to accommodate everyone.


B.

Ignore the situation since the team member is accomplishing their deliverables.


C.

Reinforce the ground rules for standup meetings with the entire team.


D.

Speak with the team member directly to reinforce the ground rules.