A project manager is managing a national rollout for an innovative product in a regulated environment that is expected to change. The project management office (PMO)

needs visibility of the regulatory constraints while maintaining a degree of flexibility.

Which tool can the project manager use?


A.

Use a burndown chart to provide transparency.


B.

Use a kanban board to increase accountability.


C.

Use a product backlog to manage changes.


D.

Use a burnup chart to provide transparency.