PMI Project-Management-Professional PMP Question # 432 Topic 45 Discussion

PMP Exam Topic 45 Question 432 Discussion:
Question #: 432
Topic #: 45

A project manager is working on a project to release a new version of a key product, The product strategy and marketing areas are still working on defining the final details for the products appearance, but the team is clear about the main features. During the last sprint review, the project sponser expressed concerns about the low quality of the product,

What should the project manager, as a servant leader, do to address this situation?


A.

Dedicate the next sprint to completing the missing details.


B.

Apply fast-track techniques to work on the missing details in parallel,


C.

Continue iterating and monitoring quality aspects sprint by sprint.


D.

Create a new risk entry for the delay in the risk management plan.