PMI Project-Management-Professional PMP Question # 439 Topic 45 Discussion

PMP Exam Topic 45 Question 439 Discussion:
Question #: 439
Topic #: 45

A company is using an agile approach to launch a new product. In the second sprint, the team encounters a technical problem they have never faced before.

What should the project manager do?


A.

Inform the project sponsor about the problem faced by the team.


B.

Ask the product owner to write the specifications for the related user story.


C.

Organize an early retrospective with the team to analyze the problem.


D.

Facilitate a problem-solving session with the team to analyze the problem.