PMI Project-Management-Professional PMP Question # 440 Topic 45 Discussion

PMP Exam Topic 45 Question 440 Discussion:
Question #: 440
Topic #: 45

A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.

What should the project manager do?


A.

Adopt the same timeframe as the closed project for the current project.


B.

inform the sponsor that the activity list is not adequate for creating a schedule baseline.


C.

Create a draft schedule based on the activity list and the historical data from the closed project.


D.

Evaluate each activity duration and build a new project schedule.