PMI Project-Management-Professional PMP Question # 449 Topic 45 Discussion

PMP Exam Topic 45 Question 449 Discussion:
Question #: 449
Topic #: 45

During a scope validation exercise toward the end of a project, a project manager realizes that some operational project requirements were not captured in the project scope of work. Although completing these Items will have an Impact on the project's completion date. It will Increase the likelihood of customer acceptance.

What should the project manager do to address the issue?


A.

Issue a change request to remove items from the scope of work and keep the project on schedule.


B.

Issue a change request to include the additional scope, and track the completion of the work items.


C.

Document the issue in the lessons learned document, and discuss this with the project sponsor.


D.

Arrange to pass the cost to the operational area since the customer will benefit.