PMI Project-Management-Professional PMP Question # 447 Topic 46 Discussion

PMP Exam Topic 46 Question 447 Discussion:
Question #: 447
Topic #: 46

A project selection committee is shortlisting projects for the coming year. Which selection criteria should the project manager recommend?


A.

Projects with the least duration


B.

Projects that maximize the business value


C.

Projects with maximum revenue generation


D.

Projects with the least associated risks