PMI Project-Management-Professional PMP Question # 456 Topic 47 Discussion

PMP Exam Topic 47 Question 456 Discussion:
Question #: 456
Topic #: 47

The Scrum team working with the quality department has been shifting away from the Business unit due to unclear product requirements. It is now the third sprint and both teams have been at a standstill for a few days.

What should the project leader do to solve this situation?


A.

Analyze the problem with both teams to figure out If pan of the work must be redone.


B.

Select new team members in an effort to obtain fresh ideas to solve the impasse.


C.

Demand that the business team stop wasting time and define final requirements for the product.


D.

Tell the business team and Scrum team to continue following the initial plan.