Question #: 459
Topic #: 47

A hybrid project team is working on an upgraded version of software for their

product owner. The team is also responsible for supporting the existing product and

customers. For the last three sprints, the team had to stop their project work and focus on

major support items for the product owner. The testers are struggling to cope with the

constant changes to the plan, which has resulted in a number of emotional outbursts.

How should the project manager proceed?


A.

Request a replacement for those team members who are unhappy with this way of

working.


B.

Schedule a session with the product owner to explain that no support items can be

taken into the sprints going forward.


C.

Ask human resources (HR) to send the team members to a change management

workshop.


D.

Schedule a session with the team to discuss the issues and work with them to define a

plan to manage the sprints going forward.