Question #: 466
Topic #: 48

A project manager has recently joined a small company. The company's chief

operating officer (COO) asked the team to skip some steps in the process in order to work

more quickly. The project manager wants to ensure that these steps are not skipped in the

future.

What should the project manager do?


A.

Notify all team members that all steps in the process must be completed.


B.

Escalate the issue to the other executive leadership members.


C.

Schedule a review of the process steps with the team and the COO.


D.

Redesign the process so the team can move more quickly.