Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 467 Topic 48 Discussion

PMP Exam Topic 48 Question 467 Discussion:
Question #: 467
Topic #: 48

A key resource is newly assigned to a project. The project manager and the resource

did not get along well in a previous project. This resource is needed to ensure the completion

of a major component for the project.

What should the project manager do?


A.

Work on resolving the differences with the key resource and building a good working

relationship to ensure project success.


B.

Monitor the key resource closely throughout the project, but do not let the project

sponsor know about the conflict.


C.

Request that the key resource's functional manager work directly with the resource

during the project.


D.

Discuss this with the project sponsor and request that this key resource be replaced on

the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.