Question #: 468
Topic #: 48

A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some

reserves needed

What should the project manager do to successfully complete the next phase?


A.

Request a reserve analysis and update the risk management plan


B.

Update the risk response plan to include the needed reserve


C.

Perform a schedule network analysis to avoid any critical path delays


D.

Review the risk response plan to verify inclusion of the needed reserve