Question #: 476
Topic #: 49

A project manager is executing a project where an external vendor will provide some deliverables Alter awarding the contract to the vendor the project manager is informed that the vendor is running behind schedule on a separate project Finding another vendor will exceed the budget

What should the project manager update first?


A.

Issue log


B.

Lessons learned register


C.

Stakeholder engagement plan


D.

Risk register