Question #: 44
Topic #: 5

During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating As a result lots of misunderstandings occurred

What should the project manager do to address this issue?


A.

Book one-on-one meetings with the team members who are not speaking up during the daily meetings to get their updates


B.

Check the ground rules of the meeting to review the initial agreement with the team members


C.

Identify one team representative to speak up during the daily meeting and share the team updates


D.

Use round-robin check-ins to facilitate the meeting so all participants have the opportunity to speak